Spring 2007 - Independent engineer Parametrix
examines Tram and proposes rebuild/replace
options and upgrades to extend its useful
operating life. Resulting engineering report is
the basis of a "design build" Request for
Proposals (RFP) issued during the summer of
2008.
-
Responsive bids received from the world's largest and only
two companies capable of performing
the specialized work - Doppelmayr and Poma.
-
After review and approval by the
RIOC Board of
Directors, a design-build contract is awarded by
RIOC to Poma in Nov. 2008 to modernize the Tram
for a 30 year design life. A Notice to Proceed
is issued by RIOC to Poma on Nov. 25, 2008.
-
Engineering, fabrication, health and safety,
government permitting processes ensue.
-
Service suspension: March 1, 2010, 2 AM
-
Tower tracks completed - September, 2010
-
New Cars arrive - September 29, 2010
-
First Car hung - October 5, 2010
-
Tramway
re-opens - November, 2010.