Roosevelt Island Tram Modernization Project

Project Milestones

  • Spring 2007 - Independent engineer Parametrix examines Tram and proposes rebuild/replace options and upgrades to extend its useful operating life. Resulting engineering report is the basis of a "design build" Request for Proposals (RFP) issued during the summer of 2008.
     

  • Responsive bids received from the world's largest and only two companies capable of performing the specialized work - Doppelmayr and Poma.
     

  • After review and approval by the RIOC Board of Directors, a design-build contract is awarded by RIOC to Poma in Nov. 2008 to modernize the Tram for a 30 year design life. A Notice to Proceed is issued by RIOC to Poma on Nov. 25, 2008.
     

  • Engineering, fabrication, health and safety, government permitting processes ensue.
     

  • Service suspension: March 1, 2010, 2 AM
     

  • Tower tracks completed - September, 2010
     

  • New Cars arrive - September 29, 2010
     

  • First Car hung - October 5, 2010
     

  • Tramway re-opens - November, 2010.

Tram Cabin

Tram Car  - winter 2009

Aerial Tramway Project Completion | A Brief History | Tram Facts | Project Benefits | Project Milestones
| Project Organization | Construction Impacts | Supplemental Transportation | FAQs

 


Copyright Copyright 2010 - Roosevelt Island Operating Corporation.   

Accessibility  Advisories  |  Contact